OWNER: City of Las Vegas
CONTRACT VALUE: $41,334,115
DURATION: 18 months
|
|
SCOPE:
- Constructing the largest single point urban interchange bridge in the valley over US 95 as well as a secondary bridge over Frontage Road
- Moving 430,000 cubic yards of roadway embankment
- Placed 8,397 linear feet of box culverts and RCP pipe
|
|
- Provided and placed 40,918 cubic yards of type 1 aggregate base and 266,459 square yards of plantmix surfacing
- Electrical work, signage and landscape beautification
- Dealt with multiple funding and inspection agencies
|